Pantai Indah Kapuk 2 (PIK 2)

Location: North Tangerang Method: Vacuum Preloading Pantai Indah Kapuk 2 is the development of a new city in north of Tangerang that originally use as fishpond area. Soft clay is found covering all over the area with depth from 8m up to 25m is the main challenge for this project....

Pantai Kita & Pantai Maju (Golf Island PIK)

Location: North Jakarta Method: Vibroflotation, Dynamic Compaction Description: Pantai Maju Golf Island a new development by Agung Sedayu Group. Located on the coast of North Jakarta with an area of around 303 hectares, it is integrated with Pantai Indah Kapuk which is connected by a fantastic 500 meter long bridge....

Jakarta – Bandung Highspeed Railway (Kereta Cepat Jakarta Bandung)

Location : Jakarta-Bandung Methord : Bored Piles & Cement-Fly Ash-Gravel (CFG) Piles Quantity : 200,000 m Description : Jakarta-Bandung highspeed railway with total 140 km length is the first high speed railway in Southeast Asia. Consist of 4 sections and 4 stations. Bored pile and CFG pile are applied to...

West Apron I Gusti Ngurah Rai Bali International Airport

Location : Ngurah Rai International Airport, Bali Method : Vibroflotation The extension of west apron at Ngurah Rai International Airport is done to accommodate International guests for IMF meeting 2018 in Bali. Due to tight schedules and work done next to fully operational airport, vibroflotation method is chosen as solution...

Dhoho International Airport, Kediri

Location : Dhoho International Airport, Kediri, Jawa Timur Method: Stone Column (SC), CFG Pile, Down-hole Dynamic Compaction (DDC) Project Duration: September 2020 – August 2022 Description : Dhoho International AirportKediri airport is the first privately developed airport in Indonesia. Located 150 kilometres south-west of Surabaya, the airfield and associated buildings...

Kijing Container Terminal, Kalimantan

Location : Kijing Container Terminal, Mempawah, Kalimantan Barat Method: PVD Vacuum Preloading Land Area : 140,000 Ha Volume : 20 Ha Project Duration: December 2018 – July 2020 Description : Operated by Pelindo II (also known as Indonesia Port Corporation), Kijing, in the Mempawah district of Pontianak port, can handle...

Amazon Data Center Karawang

Method: Bored Pile Location : Karawang, West Java Project Duration: December 2020 – October 2021...

Smelter Grade Alumina Refinery (SGAR)

Location : Mempawah, Kalimantan Barat Method: PVD Vacuum Preloading Land Area : 50,000 Ha Volume : 10 Ha Project Duration: December 2018 – July 2020 Description : Smelter Grade Alumina Refinery is a factory for smelting and processing bauxite ore into alumina which is the raw material for making aluminum...