Ibu Kota Nusantara (IKN) VVIP International Airport

Ibu Kota Nusantara (IKN) VVIP Airport is located in Penajam, Paser Utara, East Kalimantan. The clients are PT PP-BAP-RE. This is the first airport built in IKN with tight schedule which requires completion withtin 6 months period. Location : Penajam Paser Utara, East Kalimantan, Indonesia Method: PVD & Deep Cement...

Project in Ibu Kota Nusantara (IKN)

We are conducting a Bored Pile Work in several project in Ibu Kota Nusantara (IKN), such as Kemenko 2, Rusun ASN 2, Rusun ASN 4, Sumbu Kebangsaan and IKN 5B Toll Road. Location : Ibu Kota Nusantara (IKN), Indonesia Method : Bored Pile Construction Start : 2023...

Kalibaru New Priok Port

New Tanjung Priok Container Terminal is one of the busiest port in North Jakarta. Tanjung Priok Container Terminal 1B located beside the existing slab on pile terminal 1A, the container terminal 1B is an artificial island constructed from dredge slurry with ultra soft soil consistency. The original condition of island...

Lygend Smelter Aluminium, North Kalimantan

Lygend Smelter Aluminium is located in Tanah Kuning, North Kalimantan. This project is built in smelter aluminium area. We are conductin gseveral geotechnical work in order to improve the soil in this project such as Prefabricated Vertical Drain (PVD) work, Vacuum Consolidation Method (VCM) work and we’re also doing piling...

Peran PT Geotekindo pada Proyek Kereta Cepat Jakarta-Bandung “Whoosh”

Indonesia patut berbangga, sebab kereta cepat yang sudah lama diimpi-impikan saat ini telah beroperasi. Kereta cepat untuk saat ini memiliki rute Stasiun Halim Jakarta menuju ke Stasiun Tegalluar, Kabupaten Bandung yang dapat ditempuh dalam waktu sekitar 40 menit dengan kecepatan maksimal hingga 350km/jam. PT Geotekindo juga turut berkontribusi dalam progres...

Proyek Pembangunan Gedung Kemenko di IKN Terus Dikebut

Direktur Jenderal (Ditjen) Cipta Karya Kementerian PUPR Diana Kusumastuti mengatkan, progres pembangunan gedung Kemenko di IKN sudah mencapai sekitar 25 persen. Gedung Kemenko di IKN rencananya akan dibangun sebanyak 4 tower dan ditargetkan selesai pada Juli 2024. Keempat gedung Kemenko tersebut antara lain Gedung Kementerian Koordinator Bidang Perekonomian, Gedung Kementerian...

Pantai Indah Kapuk 2 (PIK 2)

Location: North Tangerang Method: Vacuum Preloading Pantai Indah Kapuk 2 is the development of a new city in north of Tangerang that originally use as fishpond area. Soft clay is found covering all over the area with depth from 8m up to 25m is the main challenge for this project....

Pantai Kita & Pantai Maju (Golf Island PIK)

Location: North Jakarta Method: Vibroflotation, Dynamic Compaction Description: Pantai Maju Golf Island a new development by Agung Sedayu Group. Located on the coast of North Jakarta with an area of around 303 hectares, it is integrated with Pantai Indah Kapuk which is connected by a fantastic 500 meter long bridge....

Jakarta – Bandung Highspeed Railway (Kereta Cepat Jakarta Bandung)

Location : Jakarta-Bandung Methord : Bored Piles & Cement-Fly Ash-Gravel (CFG) Piles Quantity : 200,000 m Description : Jakarta-Bandung highspeed railway with total 140 km length is the first high speed railway in Southeast Asia. Consist of 4 sections and 4 stations. Bored pile and CFG pile are applied to...

West Apron I Gusti Ngurah Rai Bali International Airport

Location : Ngurah Rai International Airport, Bali Method : Vibroflotation Construction Start : 2018 The extension of west apron at Ngurah Rai International Airport is done to accommodate International guests for IMF meeting 2018 in Bali. Due to tight schedules and work done next to fully operational airport, vibroflotation method...